Cambodia plans grid link for Pursat solar development
The 120-kilometre, 230-kilovolt transmission project will be backed by a US$183 million Asian Development Bank loan.

A planned transmission link in Cambodia will carry electricity from a solar development in Pursat into the national network, Mines and Energy Minister Keo Rottanak announced on November 18. Financing will include a US$183 million loan provided by the Asian Development Bank, he said.
Electricité du Cambodge will implement the project, which involves a 120-kilometre line operating at 230 kilovolts. It will serve Kandal, Kampong Chhnang and Pursat provinces, with two substations to be built and another two expanded.
The solar development being built in Pursat’s Krakor district will have combined generating capacity exceeding 1,100 megawatts. Rottanak said bringing its output onto the grid was a main objective of the transmission investment.
The project is expected to contribute to Cambodia’s clean-electricity target for 2030, set at a minimum of 70 per cent. The current share is about 63 per cent, supplied by sources including hydropower, solar and biomass.
Rottanak said the network works were intended to improve reliability and reduce outages for industrial, agricultural and residential users. He also linked expanded electricity supply to investment and employment, saying power distributed through the national network would benefit tourism, farming and industry beyond the three directly connected provinces.