Construction begins on 4.5-MW solar facility in Bali

PLN Indonesia Power says the Nusa Penida project will pair solar generation with 9 MWh of battery storage to help meet rising electricity demand.

By Arif Rahman

Solar panels and battery storage equipment on an island
Photo: Antara News

PT PLN Indonesia Power says work has begun on a hybrid solar project in Nusa Penida, Bali, with generation capacity of 4.5 megawatts (MW) and battery storage of 9 megawatt-hours (MWh). The construction schedule allows 12 months, beginning June 6, 2026.

President Director Bernadus Sudarmanta said rising local demand was one reason for the development. Nusa Penida's peak electricity load hit 18 MW in 2026, a 12 per cent increase over the previous year. He said the project was expected to produce approximately 8.8 million kilowatt-hours (kWh) annually.

Plans call for 8,608 bifacial monocrystalline photovoltaic modules on an 8.2-hectare site, with each module rated at 720 watt-peak (Wp). The batteries will use lithium iron phosphate (LFP) technology. PLN Indonesia Power expects the storage component to make solar power easier to manage and strengthen supply reliability for communities and economic activity.

Generation and storage will be coordinated using two control systems: an Energy Management System (EMS) and a Supervisory Control and Data Acquisition (SCADA) system. According to the company, these will schedule energy use, help stabilise solar output and enable electricity supply at times of high demand.