PLN secures US$2.94 billion for Indonesia’s energy transition

The financing supports its 2025-2034 electricity supply plan, alongside agreements covering hydro, solar, wind and battery storage projects.

By Arif Rahman

Solar panels and electricity transmission lines
Photo: CNBC Indonesia

Indonesia’s PT PLN (Persero) has secured US$2.94 billion in energy-transition financing at COP31 in Antalya, Turkey, to support its 2025-2034 electricity supply business plan, known as RUPTL. PLN president director Suroso Isnandar said in a statement cited on 23 November 2026 that the funding would support renewable generation and related infrastructure.

The financing involves the World Bank, Asian Development Bank, Kreditanstalt für Wiederaufbau, Agence Française de Développement, Japan International Cooperation Agency and Export Finance Australia. Part of the funding is being channelled through the Just Energy Transition Partnership platform.

PLN also signed a Mitigation Outcome Purchase Agreement, six power purchase agreements and two letters of intent for renewable-energy development. The projects cover hydroelectric, solar and wind generation, with battery energy storage systems included in some developments.

The hydroelectric projects covered are Redelong at 18 MW, Pakkat-2 at 45 MW, Besai-2 at 20 MW and Salu Uro at 95 MW. Solar projects Timor-1 and Timor-2 each have 5 MW of capacity, while Betun has 0.6 MW; all three incorporate battery storage.

The agreements also cover the 10 MW Sumbawa-Bima solar project with battery storage, plus Sulawesi Bagian Selatan (Sulbagsel) wind projects of 70 MW and 60 MW, also equipped with storage. Suroso said the power purchase agreements were an important step towards moving renewable projects from procurement into construction and investment implementation.

Separately, PLN and Princeton Digital Group are developing a green-electricity product using Time-Based Renewable Energy Certificates. The scheme allows industrial and data-centre customers to match renewable-energy attributes with actual electricity production and consumption times.

PLN is also preparing further large-scale renewable procurement under RUPTL 2025-2034. Its pipeline includes the 1.39 GW Mentari Nusantara II solar programme, the 1.3 GW Bayu Nusantara wind programme and the 2.2 GW Hydro Sulawesi programme.